How to create a data verification stage
When the M&E System Assessment form has been completed.
Select again the button with a plus icon in the “Timeline Data Entry” section. This action will allow adding a new stage and then complete it.
...
The system will display a new pop-up. The following steps must be followed:
Select data verification as program stage
Select a date
Save the form
...
The previous step will create a yellow box with the name of the current stage (Data Verification) and a light gray box with the previous stage (M&E System Assessment), both with the respective status. Under this, six sections will be displayed to respond according to each case; the six sections are:
Indicator
Availability and completeness
Data entry - accuracy - Period 1
Calculations - accuracy
Timeliness
Integrity, confidentiality and precision
...
Section: Indicator
In this section it is needed to choose which indicator will be assessed and its respective donor and project.
...
Note |
---|
. If the donor and the project are not found, select the “other” option and a new blank field will be displayed for each one to type the donor and the project. |
...
Section: Date entry - accuracy - period 1
Select the dates for starting and ending the reports. Additionally, integer number values should be typed for the three fields asked:
Start of reporting period.
Period 1 - Recount from source document.
Period 1 - Reported in platform MIS or DHIS2.
...
To add another period, select “yes” in the “Would like to add another period?” field, the new section will appear below the current section.
...