240.psi-mis.org

The main testing environment is already running at 240.psi-mis.org. The database on this environment is a copy of production, which we refresh based on the schedule below.

Refresh

DHIS2 version

Planned/ executed date

status

Late Jan

v40.3

DONE

Refresh late May

v40.4 ?

DONE

DECOMISSIONING

n/a

PLANNED

dev.psi-mis.org

dev.psi-mis.org will be upgraded to 2.40 in preparation to the go live. If you have any configuration in 2.38 that you want to move to production, please do before mid June, otherwise you will have to wait until early July so you avoid version incompatibilities. Estimated upgrade date: .

data.psi-mis.org

the production server will be upgraded after the full set of test is completed. Expected date .

clone.psi-mis.org

shortly after the successful upgrade of production (data), the clone environment, which contains a copy of production with most recent backup (last night), will become available. This could take 2 o 3 days after completing production upgrade) - estimated: .

staging.psi-mis.org

Shortly after upgrading production, the staging server DB will receive a fresh database from prod, and run v40. The staging server is used to test patch releases of DHIS2 or other changes before they are applied to prod - estimated: .

dev-mphd.psi-mis.org / mphd.psi-mis.org

Both servers are upgraded to v40.

dhis.psi-connect.org

This server is retired.

replica.psi-mis.org

The replica will be retired - The Locator API will run directly in Prod.